$42 million investment in Whitsundays electricity network complete

By Tammy Laval

A $42 million newly-completed transmission line will power homes and businesses in the Whitsunday region for decades to come.

Energy Minister Dr. Anthony Lynham said Queensland’s publicly owned electricity company Powerlink had completed a $42 million project to refit the Collinsville to Proserpine transmission line, supporting 116 jobs.

“This investment will help sustain the region’s local economy – one of Queensland’s major tourism hubs – by strengthening the transmission network’s performance,” Dr. Lynham said.

“The global coronavirus pandemic is impacting economies around the world and Queensland is no different.

“It’s pleasing to see Powerlink deliver yet another important project to play its part in powering the economy, by supplying reliable electricity to more than four million Queenslanders and supporting jobs in the process.”

The major project involved refitting more than 190 transmission towers along 76 kilometers of line supplying electricity to Collinsville, Proserpine and the broader Whitsunday area.

Built-in the late 1960s, condition assessments of the line identified a number of components needing to be refitted, largely due to corrosion from the tropical local environment.

On-ground works for the long-term project started in 2016 and were completed in stages over several years to minimise impacts on directly connected customers and the wider transmission network.

Powerlink Chief Executive Paul Simshauser said the sheer length of the Collinsville to Proserpine line made this the longest refit project undertaken by Powerlink to date.

“Our specialist crews strengthened tower foundations, replaced corroded bolts, steelwork, and insulators, cleaned and hand-painted towers, and restored anti-climbing barriers,” Mr. Simshauser said.

“Undertaking this work along 76 kilometers of line required meticulous planning and flexibility. With some towers located on large cattle grazing properties, in the Proserpine State Forest and other isolated locations, site access proved challenging.

“On-ground work was also impacted by the inevitable extended wet seasons in North Queensland, including Severe Tropical Cyclone Debbie in 2017.

“Powerlink was committed to delivering the project safely and efficiently at all times and we thank landholders and the local community for their patience while this essential work was undertaken.”

Source: Queensland Government Press Release

Up to Date

Latest News

  • New Mackay Manufacturing Hub

    The Palaszczuk Government has delivered on another election commitment today with the official opening the Mackay Manufacturing Hub. Member for Mackay Julieanne Gilbert said the new Mackay Hub would provide businesses in the region with access to development programs and specialised training. “Support for Queensland manufacturers – especially in the … Read more

    Read Full Post

  • Build-to-Rent a Queensland first

    Work is officially underway on the Palaszczuk Government’s first Build-to-Rent development, providing a boost to jobs in the construction sector and making affordable housing more accessible. Treasurer and Minister for Investment Cameron Dick today turned the sod on Mirvac’s LIV Anura Build-to-Rent development at 60 Skyring Terrace, Newstead, being delivered … Read more

    Read Full Post